Wednesday, 26 February 2014

Lego Delivered

Internal plumbing has started in the house, and we had the delivery of bricks for the ground floor yesterday. 

The bricks are a lot lighter than what we remembered! I'm a little concerned, I'm hoping that they just need a good clean or maybe they will weather over time to get their honey look that I've seen. 

We couldn't find the Brown bricks for the pillars, so maybe (and hopefully) they'll come in the next delivery. They re-completed the site fencing so we can't get back in anymore either haha! Just in time for those bricks I guess. 

They're expecting rain for the rest of the week, so I don't think they will start bricking until next week.

Cx

P.S Still no sign of that missing upstairs window...

Lego building blocks




Plumbing


Saturday, 22 February 2014

Windows and a Walkthrough

Wisdom have finished off the week with frame completed and windows installed, albeit with one missing. Not sure what happened there - must be a mistake in their order because I couldn't see a broken or spare one on site anywhere.

Love the windows. They are absolutely huge and it's one thing that freaked me out - not having enough natural light!

Most of the windows go all the way to the floor. The bathroom windows are pretty big too, they have obscure glazing though so they won't let too much in. 

We took a little tour inside the house and got to go upstairs for the first time to check out our views. We got to go into our bedroom I have no idea how we're fitting a king bed in there - it doesn't seem like enough space because the wardrobe behind takes up quite a bit of room!

The size of the bath and our spa bath provisions look really big too so that's nice to see! Also I saw that they've put in the step up for the theatre room too. 

I took plenty of pics today :) I just can't stop myself. 

Cx

Spot the missing window

Front windows in office

Podium in theatre room

Window in ground floor powder room

Laundry door


Kitchen window splashback


Dining room window

Stacker door to alfresco

Living (L) and Dining (R)


Window in theatre room

My favourite - windows with fireplace provision in between

Staircase window

Views of Mr Milburn!

Main bathroom window and bath provision

The bedroom with a missing window!

Ensuite window with bath provision and W/C window on the left


Ceiling at the entrance of the house

Outside view - theatre/powder room (GF) and ensuite and w/c (FF)

Kitchen window/splashback


Friday, 21 February 2014

We've Been Framed!

Wisdom have definitely worked their magic this week! I really didn't believe our SS when he called last week to tell us we'd have our frame up by the end of the week!

That's some crazy fast work, even with the miserable weather we've had for most of this week.

Looks like the windows have already been delivered and will be installed very soon. 

Following are pictures I've taken over the past couple of days.

Cx

Wednesdays Progress




Thursday's Progress