Sunday, 6 April 2014

Upper Eaves and Downpipes

To end what has possibly been the slowest week, we finally have upper floor eaves and downpipes installed. 

They've also managed to do a clean of the upper floor bricks.

Some issues (pictures below): chipped roof tile, holes in mortar, and poor cleanup on bricks on some places.

This month is going to kill me. This is the current timeline our SS gave us on Friday:
Mon 7th - eaves painted
Wed 9th - upper scaff comes down
Fri 11th - lower gutter/fascia installed
Tue 22nd - lower eaves and fireplace installed

I honestly can't believe it is going to take a whole month to do all that! 
Cx
























There's still mortar on bricks everywhere

Downpipe
Chipped roof tile (there's possibly more we can't see, and the displaced on we found last week still has not been fixed)

Gutter, fascia, eave 

Bad mortar job, or bad clean?

Holes in the mortar

Just looks like a mess right now!




2 comments:

  1. Our slab went down on March 6. And since then, NOTHING! The frame and windows have been delivered, and they're just sitting there, getting wet. So frustrating!!

    Donna

    ReplyDelete
    Replies
    1. Donna hi! I'm following your blog now. Congrats on the slab!!!! That is SOOO frustrating! We watched our frame get delivered and they put it up straight away. Have you heard from your site supervisor yet? This weather sucks we're definitely in wet season now, and it's still affecting us now too - progress soooo slow!

      Delete